Portfolio Timeline

Here, we will show how to configure the “Portfolio Timeline” report included in the Sample Reports (download a pdf of this guide here)

In the Power BI sample report on the Timeline tab, click on the Portfolio button.

Portfolio Timeline

Here are the fields in the order they appear

Parent Category (required)

Parent Category defines the rows in the Timeline visual.  Multiple fields can be used to display a hierarchy. Our example shows: Project Name

From the Excel data file on the Portfolio-Timeline table, we will use Project Name.

Parent Category (req)

Here is the field in the Parent Category field well:

Parent Category field

In the visual the result is:

Parent Category Result

Timeline Category (required)

Timeline Category is used to categorize both the Timeline Bars and Milestones and enables the ability to set Timeline Bar color by category, and Milestone color and shape by category. From our sample data we will use the Program Timeline Category field.

Timeline Category (req)

Here is the field in the Timeline Category field well:

Timeline Category (req)

Milestone/Task (required)

This is a True/False field that delineates between Tasks and Milestones in the data. From our sample data:

Milestone_Task(req)

Here is the field in the Milestone/Task field well:

Milestone_Task_field

Timeline Bar (required)

This field supplies the name for each Timeline bar. In many cases this will be the field used for the lowest level of the Parent Category – as in this case, we will use Project Name. Note that the visual will only use the data from the Project Name field when the Milestone/Task field is False:

Timeline Bar (req)

Here is the field in the Timeline Bar field well:

Timeline bar field

Timeline Bar Text (optional)

The Timeline Bar Text field enables the display of text in the Timeline Bar. For this example, we will use Project Name:

Timeline bar text (opt)

Here is the field in the Timeline Bar Text field well:

Timeline bar field

The text can now be rendered in the Timeline bars:

Timeline bar result

Timeline Bar Start Date, Timeline Bar Finish Date (optional)

The Timeline Bar Start and Finish dates are used by the Timeline visual to define the Timeline bar display. From the sample data we will use Project Start Date and Earliest Finish Date:

Timeline bar Start_Finish_Date

Here is the field in the Timeline Bar Start and Finish Date field wells:

Timeline bar Start_Finish_Date_field

Baseline Bar Start and Finish Dates (optional)

From the sample data, we will use If you have baseline date, these can be used to show baseline bars Project Baseline Start Date and Project Baseline Finish Date.

Baseline bar Start_Finish_Date

Here is the field in the Baseline Bar Start and Finish Date field wells:

Baseline bar Start_Finish_Date_field

Milestone

Much like the Timeline Bar field, Milestone is used to name the milestones. Again, in many cases the field in the lowest Parent Category position will be used – as in this case, we use Timeline Milestone. Note that the visual will only use the data from the Task field when the Milestone/Task field is True:

Milestone

Here is the field in the Milestone field wells:

Milestone_field

Milestone Date

Milestones only need one date, and this is where it’s needed. We will use Start Date for this field well:

Milestone_date

Data Label

Data labels can be displayed on milestones, timeline bars or both. For this example, we only want to display labels on milestones. Our data has a field called Timeline Milestone which has data for milestones but not for timeline bars (this could also be accomplished through simple DAX):

Datalabel

Here is the field in the Data Label field well:

Datalabel_field

Sort By

Sort By allows for custom sorting of your data. In the example we will not use a custom sort, so we leave that field well blank:

Sort_by

% Completion

Percent completion will display a progress bar inside a timeline bar. From our sample data we will use the P_% Complete field:

% Completion

Here is the field in the % Completion field well:

% Completion field

Timeline Bar and Milestone Tooltips

The Tooltips field wells allow you to add one or more fields to be displayed for either Timeline Bars or Milestones. For this example, we will leave them blank:

Timeline_bar_Milestone_tooltip_field

Get In Touch